SprintPlanning.md 1.86 KiB
Product Team
Responsible for building the COMMON Big Bang product.
Product Team Sprint Planning
Normal Rhythm
- Two week sprints starting on a Tuesday
- Continue to improve planning every week
- All team members who have capacity to work on the PRODUCT backlog should attend the planning session
Work Breakdown
- The Big Bang PRODUCT work will be continuously updated within GitLab by the Big Bang Product Manager, Anchors, and Anchor Shanks
- The pre-planning activity will execute the following planning steps:
- Review current team objectives
- (Re-)prioritize work at the Epic level
- Assess ( ballpark ) amount of the work the team can accomplish within the next week
- The planning activity will execute the following planning steps per planning "team":
- Review/update the currently OPEN and prioritized Epics provided by the pre-planning activity
- Decompose the Epic work into stories by writing new or updating existing stories in Jira to accomplish the Epic objectives
- Identify and capture any intra-story dependencies in Jira
- Prioritize the stories to be accomplished
- Add stories to the sprint backlog roughly equivalent to the team's capacity
Sprint Execution
- Daily PRODUCT team standup - Should discuss EPIC level issues ( dependencies, issues,etc) and be less than 15 minutes
- Daily EPIC team scrums - team members brief based on Jira Story or Task
- Review accomplishments in the last 24 hours
- Planned work in the next 24 hours
- Any blockers or helps required
- Individual Stories will be accepted
- Sprint retro ( bi-weekly to start on Thursday to inform Tues planning)
- Sprint DEMO - working software
- [FUTURE] Team capacity planning
Core Concepts
- Succeed or fail as a team
- Work pairing is highly encouraged
- Collaboration/Communication will be key to team success
- Look for ways to improve the PRODUCT and the process